Here are some interestingl jobs this year- 4 Taco Bells in different locations. The General Contractor was Shamrock Development. We worked together with them to meet their stringent time schedule. Shamrock is very committed to fulfilling their promises to their clients, such as Yum! and so are we! These were all remodels, with the exterior concrete removed and replaced with ADA compliant sidewalks and ramps. Curb and monuments for various signs, as well as block for a screen wall and dumpster, as well as the dumpster pads were also part of these assignments
Nice neat joints! |
(1) day-Remove asphalt
Remove 8" hardpan limerock
Grade/compact
(1) day- Install forms for curb perimeter
Install rebar mat
Install rebar for block at perimeter
(1) day-Pour slab
Remove forms-dress concrete
Saw with early entry saw
(1) day-Install block
Inspection
Fill block same day
Clean!